May 14, 2015
Town Administrator
Town of Walpole, NH
34 Elm Street
Walpole, NH 03608
RE: Pike Industries Resurfacing
To Whom It May Concern:
As part of NHDOT’s District Resurfacing Program, Pike Industries will tentatively be paving and performing road work on the following sections on the dates listed below. During this time, there will be times where alternating one-way traffic is necessary to perform the required work.
Roadway Section and Tentative Construction Dates:
Vilas Bridge to Main Street: 5/20/2015 – 6/19/2015
Please let me know if you have any additional questions or concerns related to this matter. I can be reached at (603) 312-6848 or ggorman@pikeindustries.com
Sincerely,
Gregory Gorman, Project Manager
Pike Industries, Inc.